Wednesday, June 20, 2012

Basement framing and LOTS of fill

 I framed and sheathed the basement walls (pretty good for a guy working  alone!) and ran the excavator for a week.  I lucked out as the fire station project just down the road generated something like 3500 yards of fill that they needed to dump nearby and I needed to improve the grading on this difficult site. That is 250 tandem loads of free fill!